SH-I  Print Work Center Schedule

Purpose of Program

Use this program to get a listing of all uncompleted sequences (operations) waiting to be performed within each work center.  The report can be sorted by Start Date or Finish Date.

The total hours backlog within the date range selected is divided by the number of hours per day available within each work center, yielding a backlog expressed in days.  This allows you to compare backlogs among work centers.

This report is often used as a daily dispatch report in the shop as a guide to which orders should be worked on next.

General Program Operation

First specify whether you want the report sorted by Start Date or Finish Date.  You can then limit the work orders that print on the report by entering X's or clearing them adjacent to various Status codes, Priority codes, and work order Class codes.  You can then enter from/thru ranges of work order numbers, Item numbers, Customers, Start Dates, and Finish Dates.  You can also have the report skip sequences for which there is no quantity.